It has been so long, I forget the sequence of events regarding
the permit process with the City of Lemon
Grove .
I do remember it taking an extremely long time to get a permit
from the City. First we needed the
grading permit. This required getting approval from the Zoning Department. We wanted to build as far up the hill as
possible, to leave as much land as possible on the other end of the lot, for a
future lot split. We also were trying to
get the house as far up hill as possible so that we would not have to pump the
sewer for the lower level.
Since we had an odd shaped lot, due to the swath of land taken
by the county by eminent domain for the now abandoned College Avenue Extension,
it was a challenge to position the house on the lot and meet all the setback
requirements. The city's map showed a cul-de-sac along the front (west) side of
the lot, ending at the top (south end) of the parcel. The Director of the Zoning Department helped
me understand that there is some zoning code that allowed in a situation like
this, to use the side yard for the front yard setback. And since it was a triangular shaped lot,
there is a code that says you measure the back yard set back from a line drawn
parallel with the front property line, and measuring 10 feet long. But we still needed to maintain a 10 foot
setback from the property line to the nearest corner of the building. Once we got all that worked out, and approved
by the Zoning Department, it was on to Engineering. That was one of the slowest and most
unpleasant aspects of the permit process.
The City Engineer would require a change to the plan. I would have my draftsman draw the change,
and resubmit it. Then it would sit on
the Engineer's desk for a week or two before he would give it back to me asking
for another minuscule change. Of course
each change would take my draftsman a week or so to draw up. So back and forth, our patience wore
thin. The final item the City Engineer
required was that we show a five foot long swale at the north corner of the
building site for rainwater runoff. The
funny part of all this is that the swale never was made, because the driveway
served for the rainwater runoff.
Plan check for the house plans went equally slow. Every required change took a week for the
draftsman and two weeks for the City plan checker. I would say that it took nearly six months to
get our plans approved and stamped so we could begin building.
In addition to the building permit fees (which included fees
for plan check, and fees calculated per electrical outlet and fixture, each
plumbing fixture, square feet of living space, square feet of garage &
storage, etc.) , we were hit with "Park Fees" of $200, and the major
expense were the school fees, which, if I recall correctly were about $2.50 per
square foot of living space. Once our
fees were paid, we were permitted to proceed with building the new house!
No comments:
Post a Comment